Extending the operational life of an Italian Power Station with an MCS II to MCS III Retrofit

17th November 2026 | Castlet

Sector: Industrial

Castlet helped a UK gypsum plant [SW1] extend the service life of its electrostatic precipitator (ESP) power equipment after more than three decades in operation.

Following an initial assessment of the installation, we developed a rolling programme to refurbish the original transformer-rectifiers and replace ageing earthing switches and high-voltage cables. The approach allowed the plant to retain its existing units while renewing the associated components that needed replacing.

THE CHALLENGE

The plant’s ESP transformer-rectifiers, earth switches and high-voltage cables had been in service since 1990. After more than 30 years of operation, the equipment was showing signs of age, and the plant needed a plan for the whole installation.

Transformer-rectifiers provide the high-voltage DC supply an ESP uses to collect airborne particles. The challenge was to determine which components could be refurbished and which needed replacing.

“The transformer-rectifiers had already given the plant more than 30 years of service. Our assessment showed there was scope to extend their working life through refurbishment. By combining that work with the replacement of the earth switches and high-voltage cables, we could give the plant a practical way to address the ageing installation in stages.”

Ian Fox, Industrial Sales Manager at Castlet

The Objective

Our objective was to extend the service life of the existing ESP power equipment. We needed to establish whether the original transformer-rectifiers were suitable for refurbishment, identify which associated components needed replacing and bring both elements together in a programme that could be delivered in stages.

Our Solution

Assessing the existing installation

We started by assessing the installed equipment to determine the scope of the work. The original transformer-rectifiers were corroded, but suitable for refurbishment, giving the plant a way to retain the units that had served the installation for many years. The ageing earth switches and high-voltage cables were identified for replacement, with all equipment showing significant signs of corrosion.

Combining refurbishment and replacement

We incorporated both elements into a rolling programme so the work could be carried out in stages. The original transformer-rectifiers were refurbished for continued service, and new earth switches and high-voltage cables were fitted. This allowed the plant to address the condition of the wider installation while making further use of its existing transformer-rectifiers.

The Outcome

The programme extended the service life of the plant’s ESP power equipment and reduced the immediate need to replace the original transformer-rectifiers across the installation. This meant that the equipment that had served the plant for years was retained, while the risks of corroded equipment were prevented. The programme took approximately six month, with the three transformer-rectifiers being refurbished one at a time, with two-day ESP shutdowns for each changeover. The plant retained the refurbished units and renewed the ageing earth switches and high-voltage cables as part of the same programme.

For the plant, the decision to refurbish meant it could continue using the original transformer-rectifiers beyond their first three decades in service. The work also addressed the associated high-voltage equipment, giving the plant a way to manage the ageing installation through a combination of refurbishment and targeted replacement.

Looking to Refurbish Ageing Industrial Equipment?

If you’re reviewing ageing ESP power equipment, get in touch with Castlet to discuss which parts of your installation could be refurbished and where replacement may be needed.

If Castlet can help you with high tech electronic solutions fill in your details below, or call

+44 (0) 1522 876 700

Get in Touch

Contact Us

Required
Required
Required
Required
Required
I’m not a robot

Solve this simple math problem:

10 – 7