Restoring ESP Operation at a Spanish Glass Plant with an Update to MCS III

23rd November 2026 | Castlet

Sector: Glass Manufacturing

Castlet upgraded the electrostatic precipitator (ESP) controls at a glass manufacturing facility in Spain during a planned one-week outage. The retrofit replaced ageing MCS II controllers with the fully supported MCS III platform while retaining the existing transformer-rectifiers.

During follow-up diagnostics, Castlet also helped the to identify and solve issues with the plant’s wider control system, an example of Castlet’s commitment to ongoing diagnostic support and problem solving.

THE CHALLENGE

The plant was operating with one of its three ESP fields out of service and had no spare MCS II controllers available. With MCS II components approaching obsolescence, the site faced growing difficulty maintaining the existing controls and had limited options if another unit failed.

The customer needed to upgrade the controls within a scheduled one-week outage. The new equipment had to integrate with the existing plant infrastructure and work with the transformer-rectifiers already on site.

“What initially appeared to be a straightforward retrofit became a wider reliability investigation. By systematically testing the installation, we were able to demonstrate that the new retrofit equipment was operating correctly and help the customer identify faults elsewhere in the control system. The result was a fully operational installation and improved confidence in the plant’s long-term reliability.”

Tom Austen, Site and Service Engineer at Castlet

The Objective

The project aimed to restore operation across all three ESP fields and give the plant a supported control platform for the long term. To make best use of the shutdown window, Castlet reviewed the existing installation and developed the retrofit plan ahead of the outage. This ensured the team were ready to implement the solution on time and on brief.

Our Solution

Designing the retrofit around the existing installation

Castlet’s engineering team designed the MCS III retrofit to integrate with the plant’s existing infrastructure, allowing the customer to retain its transformer-rectifiers. This meant that the client could upgrade their ESP controls without disrupting the core power equipment. During the one-week outage, Castlet installed and commissioned the new controls, recalibrated the system and carried out extensive testing.

Resolving wider control system issues

When reliability concerns persisted after commissioning, Castlet worked with the customer to investigate. Systematic testing verified that the new MCS III equipment was operating correctly and helped identify faults in the plant’s existing PLC/DCS system. Once those faults were assessed and rectified, all three ESP fields returned to service.

The Outcome

The plant regained full ESP functionality and moved from ageing MCS II controllers to a fully supported MCS III platform. Operators now have a colour touchscreen, enhanced diagnostics and integrated alarm logging, making it easier to review faults and configure the system.

This also provided additional technical benefits. Through additional onboard functionality, the requirements for spare parts are significantly reduced. Meanwhile, through its redundant CAN network architecture, the plant now has improved communications resilience.

The platform also gives the plant more scope to accommodate future control requirements while continuing to use its existing transformer-rectifiers. Power supply equipment was therefore retained, with just the operating system replaced.

Looking to Update from MCS II to MCS III Control?

This case is an example of Catlet’s wider capabilities, including retrofit engineering, commissioning and on-site technical support. If you’re planning an upgrade to ageing ESP controls, get in touch with Castlet to discuss your retrofit options.

If Castlet can help you with high tech electronic solutions fill in your details below, or call

+44 (0) 1522 876 700

Get in Touch

Contact Us

Required
Required
Required
Required
Required
I’m not a robot

Solve this simple math problem:

25 – 9